Since this morning, Franki Foundations has started preparatory work of nailing, to secure the existing surrounding wall.
A second phase will start in September with the realisation of 400 linear meter of diaphragm wall, divided into 50 panels, which will form the walls of the future car park.
Finally, in early 2019, we will finish with the execution of two levels of anchors, for a total of 250 anchors of 1000 kN, reinforcing the previously realized walls.
We want to thank AG Real Estate for entrusting us with the foundations work of this new emblematic project!
Header picture: contract signed between Philippe Monserez, Chief Design & Build Officer at AG Real Estate, and Wim Claesen, General Manager at Franki Foundations