Our teams have already completed:
• 169 double-rotation piles with a diameter of Ø 630 mm, at depths ranging from 13.90 m to 20.40 m, completed in just 3 weeks.
• More than 40 anchors between 8 and 14 m deep, ensuring the stability of the structure.
The next phase will be carried out by the Bauer BG45 team, who will install 59 bored piles, further demonstrating our expertise in multiple techniques and our flexibility in adapting to site constraints.
This project highlights our ability to combine technical skill, precision, and responsiveness to meet the demands of challenging projects, while contributing to sustainable mobility and improving local infrastructure.