Our teams are currently working on the reconstruction of the Ringvaart Bridge. The pile foundations for this new bridge rely on our specialized expertise.
The combination of large dimensions (piles 25 meters long, 610 mm in diameter, 760 mm drill tip), hard sand layers, and logistical constraints near the railway make this project particularly challenging. Efficiency during the temporary railway line interruptions is absolutely crucial.
Alongside the pile foundations, a test campaign for ground anchors is underway. And this is just the beginning: in the fall, our teams will also start working on the diaphragm walls for the Wondelgem tunnel.